Project Planning Maindam Bendungan Semantok Paket 1 Kabupaten Nganjuk

Project Planning of Maindam Semantok Dam Package 1 Nganjuk

ARITAMA ROCHMAWATI

The project of Maindam Work Semantok Dam Package 1 at contract price of IDR. 827.020.002.000,00 , on 1440 calendar days. An alternative project planning was needed to carry out the project on time, cost, and quality. The writer intended to make the project planning comprising the (1) organizational structure (2) site layout and traffic management (3) project quality and safety rules and, (4) implementation method, (5) cost estimate, and (6) time estimate. Technical drawings; work breakdown structure (WBS); work, material and tool unit price of Nganjuk 2017 were utilizied to find out the cost estimate. Microsoft Project 2016 was employed for scheduling through S-Curve and Microsoft Excel 2010 was used for project cost estimating. The project planning resulted in (1) functional organization (2) site layout and traffic management (3) testing material on site to meet the technical specifications and SOP (Standard Operation Procedure) and wearing Personal Protective Equipment (PPE) and setting work signs to prevent workers form accidents (4) implementation method of zone area in digging work (5) at IDR 485.998.240.027,00 (6) on 960 calendar-days.

© 2026 UPA Perpustakaan POLINEMAStatus LayananKebijakan PrivasiSyarat & Ketentuan

v2026.11.28.2 · c6ad4ed