Simulasi Monte Carlo untuk Estimasi Risiko pada Penjadwalan Proyek Pembangunan Bendungan Gondang

Monte Carlo Simulation to Estimate The Risk of Scheduling of Gondang Dam Project

KARINA RAMADHANI

Gondang Dam Project which had to be carried out within 196 weeks from May 2014 experienced a delay of approximately 28.54% in May 2017. This thesis aims to utilize Monte Carlo Simulation (MCS) to find out the mean duration in scheduling using MCS random value. The required primary data were of the results of interview with the Site Engineer Manager of contractor and secondary data were of S-Curve, shop drawings, and technical specifications. MCS was applied to find out the work mean duration using Oracle Crystal Ball software which were then used to perform scheduling using Microsoft Project and the new S-Curve in the durations of optimistic, mean, and pessimistic. The interview resulted in 43 weeks or 306 days optimistic duration and 57 weeks or 398 days pessimistic duration; the MCS resulted in 52 weeks or 369 days which is the nearest duration to the PCM duration with 5 days difference; PCM duration experiencing delay due to the equipment could not arrive on time within the last 3 years; the real schedule showing that MCS duration the most effective duration that could overcome the delay.

© 2026 UPA Perpustakaan POLINEMAStatus LayananKebijakan PrivasiSyarat & Ketentuan

v2026.11.28.2 · c6ad4ed