Perencanaan Perawatan Sistem Pelumasan Engine Excavator PC 200-7 Tipe SAA6D102E Periode 2019 s.d. 2022
Planning of Prevention System Careing on Engine Excavator PC 200-7 Type SAA6 D102E-2 Period 2019 until 2022
Lubrication is necessary in machine engine maintenance. The lubrication works to reduce friction between the moving parts in the engine block, reducing the temperature, and cleaning the engine parts. In the maintenance planning of the engine lubrication system cleaning excavator pc 200-7 type SAA6D102E-2 required some job steps based on preventive maintenance and corrective maintenance every 250 hours/meter unit operate. Based onthe planning of the lubrication system maintenance, the engine excavator pc 200-7 type SAA6D102E-2 which has been done, the maintenance schedule during one cycle treatment in the period of 2019-2022, on the in 250 hours/meter up to 12.000 hours/meter unit operation with estimation of the maintenance costs in one overhaul cycle is Rp. 341.158.181