Optimizing of Heavy Equipment in Earth Work for The Probolinggo - Banyuwangi Toll Road Project Package 1
This study focuses on excavation and embankment works on the Probolinggo–Banyuwangi Toll Road Project, Package 1, from STA 0+000 to STA 5+000. As a large-scale infrastructure project, it involves the use of various heavy equipment, each with distinct operational capacities and rental costs. Delays have occurred partly due to inefficient equipment usage and suboptimal management. To address this, the study aims to optimize the selection and allocation of heavy equipment by analyzing total costs, identifying the most economical types of equipment, and determining the optimal number of units required. The analysis uses secondary data, including work volumes, implementation plans, technical specifications, rental prices, excavation volume of 4,980.13 m³, embankment volume of 1,349,805.44 m³, and the project’s S-curve as a reference for scheduling and progress monitoring. Optimization is conducted through a comparison between manual calculations and linear programming using the LINDO application. The results indicate that the optimal total cost for excavation work is IDR 204,426,192.00, utilizing 1 unit of KOMATSU PC 200-8 excavator and 7 units of HINO 500 FC 110 JS dump trucks. For embankment work in Zone 1, the optimal cost is IDR 44,904,150,323.00 with 3 SANY SY285H excavators, 38 Hino Dutro 130 HD dump trucks, 2 Hidromek 330MG motor graders, 4 Bomag BW 161 AD– 50 tandem rollers, and 4 Isuzu NMR 71 water tank trucks. In Zone 2, the total cost is IDR 32,087,623,131.00, using 3 SANY SY285H excavators, 26 dump trucks, 2 motor graders, 3 tandem rollers, and 3 water tank trucks. This optimization ensures cost-efficiency, proper equipment allocation.