Project Planning Pembangunan Peningkatan Jalan Menuju TNBTS Kabupaten Malang
Project Planning Pembangunan Peningkatan Jalan Menuju TNBTS Kabupaten Malang
. TNBTS road widening constraction project is 23,85 km long constraction contains of road widening, overlay, drainage, and routine maintenance job. This thesist aims to make a project planning, schedule and budget of TNBTS road widening construction Kabupaten Malang. The required data includes shop drawings of the project, payroll and rent cost of Kabupaten Malang 2021, Bill Of Quantity (BOQ), and Indonesian national standard of budgeting or PERMEN PU No. 28. The method used is scheduling using bar chart on Microsoft Project, and S curve using Microsoft Excel. From the plan og budgeting and shceduling of TNBTS road widening construction project, the result shows that it could be completed within 102 working days, with an estimated cost of IDR 30.131.687.125,-